Cub Work Session #167

Today was mainly devoted to finishing up details and discussing next steps prior to painting. The overhauled instruments from Keystone arrived and it was sort of like Christmas unwrapping each one. They really look nice. Mike finished making and installing the stand-off piece to keep the trim cables from rubbing the fabric. The rudder got its final tape, so the control surfaces are almost complete. Chris continued working on the hangar's lighting, although an order of the LED lights has been delayed. The next major task will be preparing the fuselage for transport and interior painting which will be the focus of our next work session on Wednesday, May 23rd.